Eugene Investment & Securities says some of China’s largest cloud operators have cut memory orders, pressuring South Korean chip stocks including Samsung Electronics and SK Hynix; TrendForce has also cut its NAND price outlook.

Memory order cuts by some of China’s largest cloud operators are expected to keep South Korean semiconductor stocks, including Samsung Electronics and SK Hynix, in a short-term correction, according to a report published on November 26 by Eugene Investment & Securities. Analyst Son In-jun maintained an “OVERWEIGHT” rating on the semiconductor sector in the report, titled “The Period of Digesting China Risk”, citing the pullback in Greater China demand as the direct cause of the recent correction.

Why orders are being cut

The report cited several causes: shortages of GPUs and high-bandwidth memory (HBM) are delaying server construction and with it memory orders; data centre investment returns are lower than in North America and investment capacity is limited; ChangXin Memory Technologies (CXMT) is expanding its supply of server DRAM; and Android smartphone sales in Greater China are sluggish.

Export controls add uncertainty

The regulatory environment is adding to the uncertainty. The US Commerce Department’s Bureau of Industry and Security issued an interim final rule restricting even remote access to advanced AI chips through overseas data centres, which took effect on November 19. In Congress, the Remote Access Security Act has passed the House and is pending in the Senate, while the AI Overwatch Act, the Chip Security Act and the MATCH Act are under negotiation over whether they will be included in the final fiscal 2027 National Defense Authorization Act, with a decision due in December.

NAND price outlook cut in parallel

Market researcher TrendForce also cut its forecast on November 19: the expected increase in overall NAND contract prices for the fourth quarter of 2026 was lowered from 15–20% to 8–13%, and the start of the contract price decline was pulled forward from the second quarter of 2027 to the first, at 0 to −5% quarter on quarter, with all product categories entering a downward cycle from the second quarter. TrendForce said Chinese cloud providers’ cuts to 2027 enterprise SSD orders exceed the additional demand from US cloud providers; NAND industry capital expenditure is forecast at US$29.9 billion in 2027, up 26.7% year on year, with bit supply growing 25–30%. The DRAM outlook is separate: its fourth-quarter contract price forecast of +10–15% was maintained.

North American demand may absorb the volume

The report argued, however, that supply restrictions on China will not translate directly into lower global demand. North American cloud companies are still short of compute capacity and can absorb much of the volume that had been allocated to China. Estimates from the US think tank IFP show AI compute capacity available to Chinese companies growing from 4.6 million H100-equivalent units at the end of this year to 8.8 million at the end of next year, with remote use of overseas cloud services accounting for about 43% of the roughly 4.2 million-unit increase. Son also said concerns about a management vacuum at Nvidia have eased with CEO Jensen Huang’s return. (Sources: Eugene Investment & Securities, via BigGo Finance; TrendForce, via VLSI)