Ottawa LRT east extension enters full-line testing on November 22, with 23 trains running Tunney's Pasture to Trim

OC Transpo says the Line 1 east extension to Orléans will enter full-line testing on November 22, with 23 trains running between Tunney's Pasture and Trim stations for the first time, about every four and a half minutes at peak; passengers still will not be able to ride past Blair Station, and more work is needed on the traction power substation's reliability.
Ottawa's LRT Line 1 east extension to Orléans will enter full-line testing on November 22, with 23 trains running between Tunney's Pasture and Trim stations for the first time, about every four and a half minutes during peak periods — although passengers still will not be able to ride any further east than Blair Station. OC Transpo general manager Rick Leary set out the latest progress in a memo to councillors dated November 18.
Above: file photo of an O-Train at Rideau station. (Photo: Ottawa Tourism)
Software upgrade complete; full-line testing starts next week
According to the memo, software upgrades were completed on Sunday, November 15. The line was shut down during the morning to allow sub-contractor Hitachi to complete the reprogramming of the train-control software. OC Transpo then ran the system “to ensure the successful upgrade and are now ready to proceed with additional system testing.” The next phase, expected to commence November 22 with “full-line testing,” will be the first time that Rideau Transit Maintenance launches 23 trains running from Tunney's Pasture to Trim stations, operating approximately every four and a half minutes during peak periods — although passengers still won't be able to ride any further east than Blair Station.
More work needed on power substation; trial running must pass 21 days
Leary also said “additional work is still required to increase the reliability” of the LRT's traction power substation. The pre-trial running phase is expected to last about one week, followed by the trial running phase, when all train systems must meet performance, safety and reliability standards for 21 consecutive days before the extension can carry passengers. The east extension to Orléans has been long-delayed by various complications since engineers discovered a “spalling” issue in January that forced dozens of O-Train Line 1 trains offline for repairs. At a transit committee meeting in September, Leary said the extension was “progressing as planned” and that the pre-trial testing phase was forecast for early October.
Sources: CBC News, OC Transpo.