Singapore to refurbish more than 500 MRT escalators, with work starting in phases from Dec 17

· N GLOBE

Singapore's Land Transport Authority, SMRT and SBS Transit jointly announced that more than 500 escalators across four MRT lines will be refurbished to improve safety and reliability, with the first phase starting Dec 17 and completion expected in 2032.

Singapore's Land Transport Authority (LTA), SMRT and SBS Transit jointly announced on Nov 19 that more than 500 escalators across four MRT lines will be refurbished to improve safety and reliability. The first phase starts in stages from Dec 17, with completion expected in 2032.

290 escalators in the first phase, finishing in 2032

The first phase covers 290 escalators on the North-South, East-West and North East lines, with work starting in stages from Dec 17 and finishing in 2032; a further 237 escalators on the Circle Line will be refurbished later.

Four to five months per escalator

Each escalator takes about four to five months to refurbish, with work including replacement of motors, control equipment, steps, handrails and safety components. Works inside stations will be staggered, with access via upward escalators kept open and lifts remaining in service.

Background: 231 escalators already refurbished

SMRT previously spent six years refurbishing 231 escalators on the North-South and East-West lines, completing the work in 2022. This round also covers 83 escalators that were not included in the earlier upgrade plan.