Toronto's King Street West rebuild begins: 504 streetcars diverted in 10-month project running to fall 2027

The City of Toronto and the TTC began a roughly 10-month infrastructure rebuild on King Street West on Monday, replacing 139-year-old watermains before renewing streetcar tracks; 504 King streetcars are diverting via Queen Street West.
The City of Toronto and the Toronto Transit Commission (TTC) began a major infrastructure project on King Street West on Monday (November 23), expected to run until fall 2027. The work starts with replacing two 139-year-old watermains, followed by streetcar track renewal; 504 King streetcars are diverting during construction, with one lane of traffic maintained in each direction.
Five phases, starting from Dufferin Street to Close Avenue
According to a City news release dated November 20, the work proceeds in phases: Dufferin Street to Close Avenue, from November 23 to fall 2027; Spadina Avenue to Portland Street, as early as December to summer 2027; Bathurst Street to Shaw Street, spring to late 2027; and the King Street West and York Street intersection, summer 2027. The City says the phased approach is meant to limit disruption for residents and businesses, with one lane of traffic in each direction maintained during watermain replacement and access to properties preserved.
504 King streetcars divert via Queen Street as shuttle buses adjust
Since November 1, 504 King streetcars have been consolidated into a single branch running between Dundas West Station and Broadview Station. From November 23, 504/304 King streetcars are diverting via Queen Street West between Shaw Street and Roncesvalles Avenue; 504C/304C King replacement buses run between Roncesvalles Avenue and Distillery (Front Street East and Cherry Street); 503 Kingston Road buses have been extended to Dufferin Gate Loop; and 508 Lake Shore streetcars are suspended. The TTC says further service changes will follow in 2027 as the work progresses, with the latest route information at ttc.ca.
Second major disruption in two years leaves residents frustrated
It is the second time in two years that King Street West has faced a large-scale diversion for track work: the TTC carried out similar track repairs near King Street and Dufferin Street in 2025. The City and the TTC say the project is part of a joint infrastructure renewal program under way since 2020, with watermains replaced first and tracks next, coordinated in phases to avoid repeated digging. Some residents told CBC the area is "constantly being disrupted," with the World Cup construction moratorium adding to the sense of a double disruption. (Sources: City of Toronto news release, November 20, 2026; TTC King Street West project page; CBC)