Calgary's new Bearspaw feeder main built; Stage 4 water restrictions could lift next week

The City of Calgary said Thursday the new $381-million Bearspaw South feeder main is fully built and connected; the old pipe will be refilled from Nov. 27, and Stage 4 restrictions could be lifted later in the week of Nov. 30 if tests pass.
The City of Calgary announced on Thursday (November 26) that the new Bearspaw South feeder main is fully built and connected to the city's water system after 11 months of work. The old pipe will be refilled starting Friday, November 27, and if tests pass, Stage 4 water restrictions in place since November 4 could be lifted later in the week of November 30.
New pipe to enter service in late December
Before it can enter service, the new pipe must be pressure tested, cleaned, flushed and refilled, and pass water quality testing; it is expected to be operational later in December. The $381-million project began in January and was built by Ward & Burke Microtunneling and Graham Construction. Mayor Jeromy Farkas said the work was completed in under 11 months — a job many believed would take more than four years.
Refilling the old pipe takes about five days
While the new pipe is being commissioned, the city will temporarily bring the old pipe back into service: refilling starts November 27, takes about five days and requires roughly 22 million litres of water, followed by water quality testing and system checks. The feeder main supplies about 60% of the city's treated water and has burst twice since 2024. Calgary used 493 million litres of water on November 25, below the 500-million-litre daily target; daily use has stayed below target every day since restrictions began on November 4. Repairs on Parkdale Boulevard are expected to finish in early December. (Source: City of Calgary)