Nigeria breaks ground on ₦1.45 trillion Lagos ports rebuild, targeting 48-hour clearance and 20,000 jobs

· N GLOBE

Nigeria's federal government on Wednesday broke ground on a ₦1.45 trillion modernisation of the Apapa and Tin Can Island ports in Lagos, aiming to cut cargo clearance to 48 hours and create at least 20,000 jobs.

Nigeria's federal government on Wednesday (Nov. 25) broke ground on a ₦1.45 trillion (about £746 million) modernisation of the Lagos ports at a ceremony at Tin Can Island Port, rebuilding the Apapa Lagos Port Complex and Tin Can Island Port with a target of cutting cargo clearance to 48 hours and creating at least 20,000 direct and indirect jobs.

Caption: File photo: the Apapa container terminal. (Photo: Africa Harbors)

Two ministers lead the ceremony, backed by UK export finance

Marine and Blue Economy Minister Adegboyega Oyetola and Finance Minister Taiwo Oyedele jointly led the ceremony, attended by Nigerian Ports Authority Managing Director Abubakar Dantsoho, British Deputy High Commissioner Jonny Baxter and other officials. The project is backed by financing from UK Export Finance, agreed about eight months ago after President Bola Tinubu's state visit to the United Kingdom; it had previously missed two announced start dates.

Clearance takes 10 to 18 days, costing about $4 billion a year

Oyetola said cargo dwell time at Nigerian ports has ranged from 10 to 18 days, against three to five days at leading international ports, with congestion, demurrage and storage charges pushing up logistics costs and costing the economy about $4 billion a year in lost trade. The two ports handle more than 68 percent of Nigeria's container trade, but volumes are falling: Apapa's cargo throughput fell 5 percent to 535,000 tonnes in the first half of the year, with 18 fewer vessel calls, while Tin Can's calls fell 3.4 percent to 488 and vessel turnaround time rose to 5.1 days from 4.4.

Twenty berths to be rebuilt over 48 months

The works cover rehabilitation of quay walls and berths, dredging of navigation channels, improved access facilities, cargo-handling equipment and upgraded operational systems, rebuilding 20 berths; contractor ITB Nigeria's documents put the project cost at $901.86 million. The ports authority puts the construction period at 48 months, implying completion around the end of 2030. Oyetola said the Lagos works are part of a wider programme, with modernisation of the Onne, Rivers, Delta and Calabar ports also approved.